Project Update August 14, 2020
A’ building.
Under slab utilities nearing completion.
Concrete slab pour scheduled for Friday 08.21.
Service yard underground SRP conduit installation underway.
Structural steel columns set.
‘B’ building.
Masonry/CMU wall installation underway.
Scaffolding has been set and CMU walls are going up.
‘C’ and ‘D’ buildings.
Millwork, flooring, interior painting, wall hung and monitors are complete.
Classroom marker boards, tack boards, ceiling tile, ceiling lights, pre-wire for new fire alarm system all scheduled.
Exterior painting of existing window frames, doors and door frames underway.
New landscaping complete at College and Broadmor.
Toilet rooms – ceramic tile, painting, and plumbing fixtures are complete.
Lighting, toilet partitions and toilet accessories are scheduled.
‘E’ building.
Overhead and underground utilities being installed in the classrooms spaces.
Roofs are dried in.
Roof structure modifications are complete.
All new rooftop mechanical units are in place.
All new window and door openings have been cut into existing structure.
All new lintels in place.