December 1, 2020
A & B buildings.
-
CMU walls and roof structures complete.
-
Rooftop mechanical units in place on B. Roof dry-in process underway.
-
Interior stud wall framing and furring nearing completion.
-
Overhead and in-wall MP & E well underway in B. Getting started in A.
-
Preparing for metal roof system installation in B
C & D buildings.
-
Students no longer on campus.
-
Ongoing punch items.
E building.
-
Gymnasium complete for now.
-
Interior remodel spaces:
-
Stud wall framing and furring well underway.
-
Overhead and in-wall utilities well underway.
-
Structural corrections nearly complete.
-
Exterior stucco and CMU repairs and new paint scheduled.
-
Site.
-
New sidewalk, entrance drives and asphalt road patch along College Ave. complete, barricades removed.
-
Underground storm drain installation underway.
-
North parking lot concrete curbing nearing completion.
-
Parking lot light poles on site and preparing for installation.
-
CMU site screen walls and trash enclosure complete.