November 16, 2020

A & B buildings.

  • CMU walls complete in B building, substantially complete in A.

  • Roof structure and decking complete in B.  Wood roof structure and decking complete in A, steel roof structure in place and steel decking forthcoming in B.

  • Building B, Interior stud wall framing and furring ongoing.  Drywall installation starting on one side of studs.

  • Building A, interior stud wall framing and furring underway.

  • Roof dry-in, rooftop mechanical curbs and roof hatch complete at flat roofs in B.

  • Overhead and in-wall utilities well underway in B.

 

C & D buildings.

  • Students back on campus, classes in session.

  • Ongoing punch items.

 

E building.

  • Students back on campus, gym being used by student body.

  • Interior remodel spaces:

    • Stud wall framing and furring well underway.

    • Overhead and in-wall utilities well underway in E.

    • Structural corrections nearly complete.

 Site.

  • New sidewalk, entrance drives and asphalt road patch along College Ave. nearly complete.

  • Underground storm drain installation underway.

  • North parking lot concrete curbing nearing completion.

  • New drywalls complete.

  • New SRP permanent power transformer in place.