October 15, 2020

E building

 

  • Interior MP & E overhead rough-in underway, north and west areas of E building.

  • Structural steel modifications underway.

  • Final touchups and cleaning of gymnasium.

 

A & B buildings

 

  • CMU walls ongoing in building A.  

  • Steel roof structure in building B at Learning Commons ongoing.

  • Wood roof structure substantially complete in building A.  Mechanical rooftop curbs being set on A building.

  • Interior MP & E overhead rough-in being coordinated and preparing for installation.

 

C & D buildings

 

  • Preparing for return of students.

  • Punch list items ongoing.

  • Finishing exterior masonry sealer application.

 

Site

 

  • New site entry driveways and new sidewalks on College Ave. ongoing.  Same for new concrete curbs and gutters.

  • North parking lot curbing complete for now.

  • New sanitary sewer manholes west of College Ave. underway.

  • Site storm drain installation underway.

 