September 14, 2020

  • Existing ductwork in the gymnasium has been removed.  New ductwork and lights will be installed.

  • Existing locker rooms are being demolished. Existing exterior walls are being saw cut for new windows and doors.

  • Existing gymnasium lobby toilet room being demolished.  Remodel work to begin soon.

  • Demolition complete in 1009 and 1010 toilet rooms.

  • 1009 and 1010 classroom space remodel ongoing.

  • New site sewer line on south and east sides of 1010 is installed and being backfilled.

  • Buildings A and B.  Footings are dug and rebar installed, along with column anchor bolts.

  • Concrete started being poured today for footings for A and B.  Footing concrete will finish next week.

  • Once footings are complete, A and B are moving on to stem walls and under slab utilities. 